More Street Resurfacing in Evanston Starting July 29

The city will be doing street resurfacing work on seven areas around Evanston starting next Monday.

The City of Evanston will be doing street resurfacing work in seven areas around the city as part of the Capital Improvement Plan, with work starting the week of July 29 and lasting for about nine weeks, according to a press release.

The locations included as part of this work will occur in the following order:

• Prairie Avenue (Harrison Street to Central Street)

Find out what's happening in Evanstonwith free, real-time updates from Patch.

• Prospect Avenue (Colfax Street to Grant Street)

• Wesley Avenue (Foster Street to Dead End North)

Find out what's happening in Evanstonwith free, real-time updates from Patch.

• Foster Street (Maple Avenue to Sherman Avenue)

• McDaniel Avenue (Lee Street to Dead End North)

• Dewey Avenue (Mulford Street to Kirk Street)

• Hartrey Avenue (Howard Street to Dead End North)  

The project involves curb replacement as needed, roadway base repair, replacement of asphalt surfaces from curb to curb and the replacement of selected sidewalk and driveway aprons. As part of this project, a drop-off zone will be constructed on east side of Prairie Avenue in front of Haven Middle School.

The street resurfacing work is part of the city’s program to renovate and improve the roadways throughout the community. The funding for the project will be from the city’s Capital Improvement Plan Fund.

The actual date when construction is planned for each street will be noted on temporary NO PARKING signs that will be posted 48 hours prior to the start of work. 

Construction zone daytime NO PARKING restrictions will be intermittent throughout the duration of the project; evening and night time parking (5:00 p.m. to 7:00 a.m.) will always be available.

Street sweeping and/or neighborhood parking restrictions will be waived for a one-block radius around the construction zone when temporary daytime NO PARKING is in effect. 

Any sprinkler system should be identified and marked with a flag by the property owner prior to the start of construction to prevent damage.

The contractor for this project is A. Lamp Concrete Contractors, Inc., 1900 Wright Boulevard, Schaumburg, IL 60193.

The Resident Engineer in the field will be Angeleo Alonzo Jr., who will by responsible for all aspects of the construction. If residents should have any questions or concerns, they can contact the Resident Engineer by calling 3-1-1. Questions about the street project in general should be directed to Sat Nagar, P.E., Senior Project Manager at 3-1-1.